- Administrative Home
- Phase 10A
- RSG
- PopulationSim Dependency Update
- Sub-Model Preprocessing and Annotating Consistency
- CS / Jeff
- Specification performance analysis tool
- Skim Variables Input Check
- Validate all input files for all components before running anything
- WSP
- Multi-year Development Roadmap
- TBD
- Design for econometrically consistent simulation
- Compatibility with Pandas 2.x?
- RSG
- No updates
- No significant comments/edits on provided scopes (shown under Agenda)
- Need to scope out TBD items
- Design for econometrically consistent simulation
- Need to think through ways to design changes by Engineering team
- Joe thinks addressing this issue will be a big improvement to ActivitySim
- Suggest having an overall budget task and then distribute to team members with slightly more budget for firm that is leading the task
- Person should lead the Product team and a person leading the Engineering team
- Should include pros and cons and recommendations from Product team and an overall Engineering team
- Should have multiple design options and really consider them, including prototyping them to ensure they can work or to see any issues
- This will be one of the biggest changes to software, so need to make sure we do it right
- Consultants to get together to work through scope and budget for the task; cc Joe and Alex on meeting invite
- Will deliver before the holidays
- Sijia will write first draft and send early next week
- Compatibility with Pandas 2x
- Jeff has not had a chance to review; If he can review then will add to Phase 10A, otherwise it may wait till Phase 10B
- PopSym - David will ensure issues that were brought up are addressed as part of Phase 10A task order
- Reviewed pull requests for approval