- UrbanLabs (@e-lo) under contract
- Still waiting on OSG - Ben (@bstabler) to email OSG
- GitHub repo
- RSG and the MPO team are now all activitysim owners
- All activitysim team members are members and have admin on the activitysim repo
- Ben and Jeff can now take ownership of the repo, the webhooks, etc.
- Will write protect the master branch and require automated testing Issue #64
- Dave (@DaveOry) working on a governance plan for activitysim
- Will manage the project pretty much entirely on GitHub
- Ben and Jeff out week of 3/21; Ben still have meeting 3/25
Jeff (@toliwaga) and Ben talked with Fletcher (@fscotfoti)
- Discussed mostly big picture software framework ideas, project goals, the previous project, etc.
- Discussed required skills for a user and a developer and how that informed the design
- Discussed skimming API a bit
- Ben will setup another call in a couple weeks since we didn't discuss a lot of technical stuff yet
-
Getting Started Tutorial - We will start with Fletcher's website material (in the docs folder) and use the same github pages solution - Ben was interested in using the linked project wiki since it is more accessible/convenient, but this will be for project admin - Will focus on a model user and will use the included example - Will not require the user to modify stuff in activitysim - A second "developer" tutorial will be a deeper dive into modifications for new modules, etc.
-
- Dave will post all the MTC TM1 matrices for RSG; Ben will convert to OMX
- We will start with un-commenting out a couple of Fletcher's skims API edits to use just one matrix
- Will run tour mode choice and see what performance looks like
- Creating a benchmark at this point
- Won't refactor code at this point; focused more on review, design ideas, benchmarks, etc.
- Travis doesn't support all the matrices, so this is something to consider
- Once up and running, will work on some additional testing for the various skim queries:
- one OD pair
- one O to all Ds
- one O to a sample of Ds
- all Os to Ds
- by mode, time-of-day, etc.
- etc.
- Dave started on an accessibilities calculator for travel model one that is housed on his github page; this will be useful to review
-
Coveralls Testing via Continuous Integration System
- Now that RSG has admin on the repo, we will take ownership of the Travis integration and make sure everything is working
Progress on the three Task 2 work items