- Joe finalizing scope with each bench contractor
- Hopes to get Phase 6b executed by 6/11
- Working on tidying up for the v1 release:
- Update docs and notebooks for improvements
- Work from home and telecommute frequency submodels
- Transit pass ownership and pass subsidy submodels
- Autocalculation of chunking (#406)
- Jeff Newman proposed a more systematic approach to benchmarking for Phase 6b that would be good to implement for future work such as this
- Improved checkpointing of tables (#405)
- This is a useful feature and something that could have been improved in DaySim
- Agencies likely to just use an ActivitySim example as a starting point rather than directly translate their CT-RAMP or DaySim setup
- Smarter logging when no alternative found (#404)
- Additional items for release
- Update to conda forge for environment setup? (#424)
- Jeff Newman to work on after this release; for now it seems to work well enough as is
- Will make ActivitySim a conda forge repo, which will simplify install
- Fix full scale example downloads for skims*.omx issue (#421)
- Other little stuff, (#414), (#425)
- Update to conda forge for environment setup? (#424)
- Soon merge all to develop
- Need to update the transit pass model google doc
- Update docs and notebooks for improvements
- SEMCOG team working on implementing the full scale new submodels
- Next week Wu share SANDAG's 1, 2, and 3 zone system testing progress