- General Admin - Administrative transition
- General Admin - Phase 10A tasks
- Announcement: A bug fix release v1.3.2 has been made, to address problem with setting the location of the sharrow cache directory.
- Admin - Payments
- Still waiting payment from ARC, CMAP, Translink, and MetCouncil
- MetCouncil thinks payment was made
- ARC payment is in progress and will be made tomorrow to AMPO
- Still waiting payment from ARC, CMAP, Translink, and MetCouncil
- Admin Transition/Home
- AMPO and Consortium discussed level of effort of various admin tasks.
- Narrowed it down to a window/range of that level of effort
- Kanti will meet with AMPO tomorrow to discuss further
- University option is still on the table, but there are reservations about that idea
- Need to make a decision very soon on what we pursue
- If we stay at AMPO, it would be good to have a firm commitment on how many years AMPO will commit to the agreement
- Independent option
- Need to establish ourselves as non-profit, take a few months
- Feb 2025 would have organization set-up and then need to do a lot of Admin stuff
- Contract w firm that works w/ non-profits to do Admin stuff: Bank account, accounting, legal council
- Spring 2025 - vendor/consultant contracts, MOA & Funding agreements
- June 2025 - final transfer from AMPO (transfer funds), new website
- Other options still on table as well
- Not ideal: AASHTO, NARC, Federal pooled fund, Volpe, Rand (not interested), decentralized, program manager
- TTI - very enthusiastic, want to integrate their own work w/ ActivitySim, but there may be challenges working with institutions including autonomy
- Mat Hardy at ITE, said there may be an opportunity to partner with ITE and TTI on ActivitySim
- Zephyr - less autonomy than stand-alone non-profit option; easier to ramp-up
- No one has criticized Zephyr as being an option
- Really important to get consensus on path forward
- AMPO and Consortium discussed level of effort of various admin tasks.
- Phase 10 Scoping
- Agencies should take look at Phase 10 Priority list and way in on priorities for Phase 10, see Project List
- Tuesday - focus on Phase 10A Scoping
- Thursday - continue discussion of Administrative home