Update Major and Stabilization Process to indicate all repos and clarify Feature List #149

Merged
merged 4 commits into from
Mar 27, 2023
Merged
Show file tree
Hide file tree
Changes from all commits
Commits
File filter

Filter by extension

Filter by extension

Conversations
Failed to load comments.
Loading
Jump to
Jump to file
Failed to load files.
Loading
Diff view
Diff view
12 changes: 8 additions & 4 deletions releases/Process/Major Release Process.md
Original file line number Diff line number Diff line change
Expand Up @@ -17,6 +17,7 @@ The release process is managed by the Release Special Interest Group (SIG). To r
* o3de-multiplayersample
* o3de-netsoaktest
* o3de-extras
* o3de.org


## Roles and Responsibilities
Expand Down Expand Up @@ -74,8 +75,8 @@ Entry Criteria: Release SIG has has indicated the need for a release and has a g
6. **Release Manager** ensures all Planning tasks on the project board are completed, either by completing them or assigning them to others.
7. **Release Manager** has a Planning task on the project board to identify all Release Roles. These release roles should be updated in the Key Information once known.

### 1.2 Beginning work on the Feature List
The Feature List usually begins 6-8 weeks prior to release. See [Terminology](#terminology) for description of the Feature List.
### 1.2 Create the Feature List
The Feature List usually begins 6-8 weeks prior to release and ends 1-2 weeks after stabilization begins. See [Terminology](#terminology) for description of the Feature List.
Entry Criteria: A Pre Release task exists to generate the Feature List, similar to https://github.com/o3de/o3de/issues/11100

Note: This is a highly manual process. There is an opportunity to improve. See Appendix A,
Expand All @@ -88,8 +89,9 @@ For pre-release step (4) "Review closed issues to see if anything else should be
* For each roadmap item delivered to the o3de codebase since the last release, enter a summary into the feature list.
* If you need assistance, comment under the GHI or reach out to the SIG owning that area of the engine
* (Optional) Review the submitted pull requests or closed Github Issues. The reason to do this would be to discover any features that were not on the Roadmap, potentially features that were accidentally missed.
3. Once you have created the feature list, post a note to #sig-all in discord requesting the SIGs to review and update if needed via Pull Request.
3. Once you have created the feature list, post a note to #sig-all in discord requesting the SIGs to review and update if needed via Pull Request. Allow Pull Requests to the Feature List until 1-2 weeks after Stabilization begins (agree on a date with the Documentation Project Manager).
4. Notify the marketing committee once the feature list is mostly (80%) done (you have some input from each SIG, and they indicate that they "most" of their work submitted). They may ask for a summary of the release and key features. It is up to the release manager to provide this guidance to the marketing committee. The release manager may discuss with the Release SIG or any other SIG to figure this out.
5. Once you reach the date to stop accpeting PRs to the Feature list. Notify the Documentation Project Manager to take the feature list and begin the Release Notes. From this point forward, any changes needed to the release documentation should be done by coordinating with the Documentation Project Manager.

### 1.3 More about how Milestones are used
For each release, Github milestones are used to track bugs found in the stabilization branches of each repo involved in the release. For example, for the 22.20.0 release, the [Release/2210 milestone](https://github.com/o3de/o3de/milestone/11) captures all of the bugs found during release stabilization of the O3DE repo.
Expand Down Expand Up @@ -148,7 +150,9 @@ The Documentation Project Manager is responsible for the following items:
* **C++ API Reference Generation**
* **Documentation Versioning**
* **Version Information**
Each of these tasks are further explained in the [Docs Release Process](./Docs%20Release%20Process.md).
Each of these tasks are further explained in the [Docs Release Process](./Docs%20Release%20Process.md).

The **Release Manager** is responsible for reviewing the release notes once available. This review should happen prior to release. This corresponds to a task in the release project board.

*Exit Criteria: All Pre-Release Steps are complete*

Expand Down
3 changes: 2 additions & 1 deletion releases/Process/Stabilization Process.md
Original file line number Diff line number Diff line change
Expand Up @@ -13,8 +13,9 @@ O3DE Stabilization is the process we use to prepare the codebase for a release.
- Stabilization involves the following O3DE Repositories:
- o3de
- o3de-multiplayersample
- o3de-test
- o3de-netsoaktest
- o3de-extras
- o3de.org