Focus follows a 2-week sprint cycle with 6-week milestone releases. Dot-releases with bugfixes are released every two weeks. Our upcoming train schedule is here.
Priority labels are based on the Bugzilla triage process and set during triage to determine when they'll be worked on:
P1
: Issues for the current 2-week sprint.P2
: Issues for the 6-week milestone release.P3
: BacklogP5
: Will not fix but will accept a patch
Other labels:
addressed
: Label for excluding items from triage. Should be used for [meta] items.
-
[meta]
: larger issues that need to be broken down, into a[breakdown]
issue and issues for its smaller parts. This should include a checklist of all the issues (including the[breakdown]
issue).These do NOT get a P* label, but should be in a milestone.
-
[breakdown]
: issue to track the work of breaking down a larger bug
- (Link) Assign priority labels (P1, P2, ...) to bugs without priority labels or the
addressed
label - (Link) Ensure all P1 labels are assigned a milestone
- (Link) Ensure all P2 labels are assigned a milestone
Deciding what goes into a sprint, promote P2 issues to P1. After every release, this meeting is for deciding what goes into the upcoming milestone - add issues to the milestone and set them as P2.
Handling Triage overflow, adding to the contributor bug lists, looking at milestone lists.
Plan and prioritize features for upcoming milestones - an update will be emailed out.
Plan and facilitate workweeks release schedule trying to work with things without proper training too much observing