Meeting Date/Starting Time: Nov 5, 20:20
Meeting Purpose: Weekly catch-up, planning ahead
Meeting Location: CMPE Building A4
People who attended:
- Mert Yüksekgönül
- Yunus Emre İnci
- Fatih İver
- Muhammet Furkan Gök
- Özgür Solak
- Harun Eren
- Alperen Kürşad Özkan
- Rukiye Dilruba Köse
Item | Description |
---|---|
1- Evaluation of Last week | • How did the requirement oriented plan go? • How to do better in general? |
2- Milestone2 Coming Up | • What would we like to have for milestone2? |
Item | Notes |
---|---|
** 1- Last Week ** | • We cannot complete pages for frontend since we need few more backend endpoints. We will give higher priority to complete specific pages. |
** 2- Milestone2 ** | • We are hoping to complete all/or most of the user requirements in 3 weeks. |
** 3- Dates ** | • Are all of the dates kept in the database in the same format? If not, we need to fix it. |
** 4- Fetching parity data ** | • We are going to use AlphaVantage with replacing the API key periodically, since there is no API for parities with infinite number of requests. |
** 5- Frontend Milestone ** | • Weekly Req: Equipment page, event page, parity page, create/edit/delete article/comment. |
** 6- Backend Milestone ** | • Weekly Req: Comment like, parity data fetchleme, event data fetchleme, portfolio, prediction API, register IBAN check |
** 7- Mobile Milestone ** | • Weekly Req: Event, equipment. |
Done? | Item | Responsible | Due Date |
---|---|---|---|
✔️ | 1- Meeting Notes for Meeting#18 | Mert | Dec 05, 10:00 AM |
- Requirements
- Mockups
- User Types
- Personas, User Stories and Acceptance Criteria
- Use Case Diagrams
- Class Diagram
- Sequence Diagrams
- Milestone Report #1
- Project Plan
- System Manual
- User Manual
- TrAiders Annotation Server