This section outlines the planned release schedule and key milestones for the FOCUS project. It includes the scope and high-level system requirements for each version, as well as detailed timelines for the development and review processes for each present and past releases.
Version | Release By | Scope | High-Level System Requirements |
---|---|---|
v1.1 | Nov 11, 2024 |
SKU and SKU Price Details
|
v1.2 | Mid, 2025 |
REQ 4: Keyword value/brief description REQ 5: Keyword value/brief description REQ 6: Keyword value/brief description |
v1.3 | Late, 2025 |
REQ 7: Keyword value/brief description REQ 8: Keyword value/brief description REQ 9: Keyword value/brief description |
This table displays key milestones and dates related to the development of FOCUS Release v1.2 Specifications.
Date | Milestone | Comment |
---|---|---|
8-Oct-24 | Start Work Item Preparation | For Release v1.2, the group will implement a new process for creating Work Items. |
8-Oct-24 to 21-Nov-24 | Work Item Creation | Six weeks (6) to develop the FOCUS Release (Rel) v1.2 scope. |
21-Nov-24 to 3-Apr-25 | Development Phase | Nineteen weeks (19) to develop FOCUS Rel v1.2 specifications. |
23-Jan-25 to 6-Feb-25 | Interim Consistency Review | Two weeks (2) for the Interim Consistency Review of FOCUS Rel v1.2. |
3-Apr-25 | End Development Phase | End of FOCUS Rel v1.2 development. |
3-17-Apr-25 | Consistency Review | Two weeks (2) for the Final Consistency Review of FOCUS Rel v1.2. |
17-24-Apr-25 | Preparing baseline for IPR Review | One week (1) of preparation to start the IPR Review. |
24-April-25 to 24-May-25 | Start / End IPR Review v1.2 | During this 30-day period, members may exclude essential claims from their licensing commitments. Contact the FOCUS Executive Director. |
29-May-25 | WG Approval v1.2 | FOCUS Release Candidate v1.2 approved by the FOCUS members. |
29-May-25 | SC Ratification v1.2 | FOCUS Steering Committee ratifies Rel v1.2. |
3-Jun-25 | FinOpsX Announcement | FOCUS Rel v1.2 must be ready for announcement sometime in June. |
This table displays key milestones and dates related to the development of FOCUS Release v1.1.
Date | Milestone | Comment |
---|---|---|
16-May-24 to 19-Sep-24 | Start / End of the Development FOCUS Rel v1.1 | 17 weeks to develop FOCUS Rel v1.1 |
18-Jul-24 | Approval FOCUS v1.1 Scope | Close the scope for FOCUS Release v1.1 |
18-Jul-24 to 1-Aug-24 | Start / End Interim Consistency Review | CANCELED Two weeks Interim Consistency Review FOCUS Rel v1.1 |
19-Sep-24 to 08-Oct-24 | Start / End of the FOCUS Rel v1.1 Final Consistency Review | Two weeks Final Consistency Review FOCUS Rel v1.1 |
03-Oct-24 to 08-Oct-24 | Preparing FOCUS Rel v1.1 baseline for IPR Review | Five days to get ready the baseline Specifications for IPR Review |
08-Oct-24 to 07-Nov-24 | Start / End of IPR Review v1.1 | During the 30-day period, members may exclude essential claims from their licensing commitments. |
07-Nov-24 | WG Approve v1.1 | FOCUS Release Candidate v1.1. Approved by FOCUS Members |
07-Nov-24 | SC Ratification v1.1 | FOCUS Steering Committee Ratifies v1.1 |
11-Nov-24 | FinOpsX Europe Announcement of v1.1 | Announcement of FOCUS Release v1.1 during the FinOpsX Europe Keynote (Barcelona) |
FOCUS Release V1.1 will be announced during the FinOpsX event in San Diego on June 20, 2024.
Date | Tasks | Comments |
---|---|---|
Feb 28 - Mar 11 | Consistency Review | Opportunity for everyone to review what has been agreed upon in the working-draft branch. Lock scope for v1.0. |
Mar 12 - Apr 25 | Drive v1.0 milestone issues to completion | Incoming issues will be prioritized by maintainers. Only P0 and some P1 issues will get added to the v1.0 milestone. Prioritization will take voting and comments in issues into consideration |
Apr 25 - May 09 | Final Consistency Review | Freeze working-draft. Final review, only expecting editorial comments. |
May 13 - June 11 | IPR Review | Members may exclude any Essential Claims from their licensing commitments during this period. |
June 13 | Release Candidate Approve by the WG Members | |
Jun 19 | Steering Committee Ratifies the Release | |
Jun 20 | FinOps X: Onstage FOCUS Adoption stories |